TRAMWAY WORKS SUMMER 2024

Lines B, C and E

During 4 successive periods between Monday June 24 and Friday August 23, 2024 inclusive, CTS is carrying out maintenance work on the tracks of lines B, C and E.

 

Stage 1 : From 24 june to 12 july 2024.
Tram lines C and E suspended between Esplanade and Landsberg.
Replacement bus between Esplanade and Jean Jaurès.

 

Thermo C_E - Esplanade Landsberg_Phase 1

 

Stage 2 : From 8 to 21 july 2024.
Tram line B suspended between Wacken and Hoenheim Gare.
Replacement bus between Wacken and Hoenheim Gare.

 

Thermo ligne B - Wacken HG_Phase 2

 

Stage 3 : From 22 july to 9 august 2024.
Tram lines B and E suspended between République and Hoenheim Gare / Robertsau L’Escale.
Replacement bus between République and Hoenheim Gare / Robertsau L’Escale.

 

Thermo lignes B_E-République HG RE_Phase 3

 

Stage 4 : From 8 to 21 july 2024.
Tram lines B and E suspended between Wacken and Hoenheim Gare / Robertsau L’Escale.
Replacement bus between Wacken and Hoenheim Gare / Robertsau L’Escale.

 Thermo lignes B_E-Wacken HG RE_Phase 4

   